Energy-Efficient Renovation of Sundern Indoor Pool

Published on 16. July 2026

The following work has been completed or is currently underway:

  • Interior and exterior scaffolding
  • Asbestos abatement completed; building has been cleared for re-entry
  • Demolition of structural concrete elements and clinker facade is finished
  • Parts of the roof structures have already been structurally reinforced and renovated
  • The pent roof was demolished following the structural work, and the supporting shell is currently being replaced
  • Concrete restoration is still in progress
  • Metalwork and glazing work are underway
  • Plumbing work is underway
  • Drywalling and acoustic ceiling work have been commissioned
  • Ventilation technology has been commissioned
  • Swimming pool technology will be commissioned shortly
  • The electrical tender is currently in progress

Based on the current status, construction measures are scheduled to be completed by January 2027.